San Francisco Public Utilities Commission (SFPUC)
The San Francisco Public Utilities Commission (SFPUC) provides and distributes water to 2.6 million customers, treats wastewater, and supplies electric power to operate Muni streetcars and electric buses, street and traffic lights, and municipal buildings. The amount of facilities and infrastructure it takes to accomplish its mission is vast, including 16 dams, 25 reservoirs, eight water tanks, three water treatment plants, 933 miles of sewers, 160 miles of transmission lines, and over 150 miles of pipelines. This complex network of infrastructure is managed by three utility enterprises within the SFPUC: Water, Wastewater, and Hetch Hetchy Water and Power.
SFPUC: Water Enterprise | FY 2022 | FY 2023 | FY 2024 | FY 2025 | FY 2026 | FY 2027 - 2031 | Plan Total | |
SPENDING PLAN | DEFERRED | |||||||
Regional Costs | ||||||||
Water Treatment Program | 12,546 | 136,614 | 89,891 | 16,079 | 10,841 | 6,502 | 272,473 | |
Water Transmission Program | - | 15,629 | 26,955 | 23,379 | 22,829 | 58,432 | 147,224 | |
Water Supply & Storage Program | 29,842 | 35,280 | 35,710 | 56,371 | 60,280 | 123,828 | 341,312 | |
Watersheds & Land Management | 14,861 | 2,812 | 2,350 | 2,350 | 2,355 | 11,790 | 36,518 | |
Communication & Monitoring Program | 482 | 500 | 725 | 1,515 | 565 | 3,875 | 7,662 | |
Buildings And Grounds Programs | 2,000 | 11,967 | 74,930 | 59,462 | 2,200 | 11,065 | 161,624 | |
Long Term Monitoring & Permit Program | 4,000 | 3,457 | 3,374 | 1,782 | 1,538 | 8,302 | 22,453 | |
Regional Subtotal | 63,731 | 206,259 | 233,936 | 160,938 | 100,608 | 223,795 | 989,266 | |
Local Costs | ||||||||
Water Supply Projects | 6,700 | 500 | 500 | - | - | - | 7,700 | |
Local Water Conveyance/Distribution System | 71,351 | 57,405 | 82,116 | 77,875 | 56,908 | 264,582 | 610,238 | |
Local Tanks/Reservoir Improvements | 5,265 | 350 | 350 | 350 | 350 | 12,475 | 19,140 | |
Pump Station improvements | 200 | - | 500 | 1,500 | 450 | - | 2,650 | |
Recycled Water Projects | 4,665 | - | - | - | - | - | 4,665 | |
Automated Meter Reading System | 2,970 | 3,222 | 3,012 | 3,162 | 3,162 | 12,051 | 27,579 | |
Buildings & Grounds Improvements - Local | 34,500 | 17,724 | 119,465 | 134,818 | 37,403 | 3,013 | 346,923 | |
Local Subtotal | 125,651 | 79,202 | 205,943 | 217,705 | 98,273 | 292,121 | 1,018,895 | |
TOTAL | 189,382 | 285,460 | 439,879 | 378,643 | 198,881 | 515,915 | 2,008,161 | |
REVENUES | ||||||||
Revenue | 55,658 | 67,100 | 72,100 | 77,100 | 82,100 | 298,473 | 652,531 | |
Revenue Bonds | 132,204 | 216,840 | 366,259 | 300,023 | 115,261 | 209,386 | 1,339,975 | |
Capacity Fee | 1,520 | 1,520 | 1,520 | 1,520 | 1,520 | 8,056 | 15,656 | |
TOTAL | 189,382 | 285,460 | 439,879 | 378,643 | 198,881 | 515,915 | 2,008,161 | |
Total San Francisco Jobs/Year | 848 | 1,279 | 1,970 | 1,696 | 891 | 2,311 | 8,995 | |
SFPUC: Wastewater Enterprise | FY 2022 | FY 2023 | FY 2024 | FY 2025 | FY 2026 | FY 2027 - 2031 | Plan Total | |
SPENDING PLAN | DEFERRED | |||||||
Sewer System Improvement Program | ||||||||
Program Wide Management | - | 7,000 | 10,000 | 9,143 | 14,000 | 59,000 | 99,143 | |
Treatment Facilities | 333,552 | 247,132 | 248,142 | 191,222 | 154,063 | 318,016 | 1,492,127 | |
Sewer/Collection System | 15,048 | 72,494 | 44,959 | 73,723 | 87,687 | 570,526 | 864,436 | |
Stormwater Management/Flood Control | 37,544 | 162,263 | 106,984 | 127,207 | 90,912 | 170,331 | 695,241 | |
SSIP Subtotal | 386,144 | 488,888 | 410,086 | 401,296 | 346,661 | 1,117,872 | 3,150,947 | |
Renewal & Replacement | ||||||||
Collection System - Condition Assessment | 7,999 | 9,574 | 11,688 | 11,496 | 12,070 | 62,280 | 115,106 | |
Collection System - Sewer Improvements | 107,704 | 102,608 | 106,715 | 98,217 | 102,219 | 553,260 | 1,070,723 | |
Collection System - Large Diameter Sewer | - | 2,550 | 29,402 | 31,959 | 47,709 | 268,173 | 379,793 | |
Treatment Plant Improvements | 26,625 | 27,957 | 29,354 | 30,822 | 32,363 | 186,982 | 334,104 | |
Renewal & Replacement Subtotal | 142,328 | 142,689 | 177,159 | 172,494 | 194,361 | 1,070,695 | 1,899,726 | |
Wastewater Facilities & Infrastructure | ||||||||
Ocean Beach Protection | 2,417 | 45,000 | 47,000 | 33,523 | 13,233 | 4,838 | 146,011 | |
SWOO Condition Assessment & Rehab | - | - | - | 1,313 | 1,313 | 27,974 | 30,600 | |
Southeast Outfall Condition Assessment & Rehab | - | - | - | 1,459 | 1,459 | 28,702 | 31,620 | |
Islais Creek Outfall | - | 5,761 | 3,890 | 2,878 | 509 | 3,715 | 16,753 | |
Wastewater Facilities & Infrastructure Subtotal | 2,417 | 50,761 | 50,890 | 39,174 | 16,514 | 65,230 | 224,985 | |
Treasure Island | 15,000 | 80,000 | 52,810 | - | - | - | 147,810 | |
TOTAL | 545,889 | 762,338 | 690,945 | 612,964 | 557,536 | 2,253,798 | 5,423,469 | |
REVENUES | ||||||||
Revenue | 110,252 | 122,657 | 125,111 | 127,613 | 130,165 | 690,931 | 1,306,729 | |
Revenue Bonds | 430,317 | 633,986 | 560,139 | 479,656 | 421,676 | 1,534,391 | 4,060,166 | |
Capacity Fees | 5,319 | 5,695 | 5,695 | 5,695 | 5,695 | 28,475 | 56,574 | |
TOTAL | 545,889 | 762,338 | 690,945 | 612,964 | 557,536 | 2,253,798 | 5,423,469 | |
Total San Francisco Jobs/Year | 2,445 | 3,415 | 3,095 | 2,745 | 2,497 | 10,095 | 24,292 | |
SFPUC: Hetch Hetchy Water and Power | FY 2022 | FY 2023 | FY 2024 | FY 2025 | FY 2026 | FY 2027 - 2031 | Plan Total | to |
SPENDING PLAN | DEFERRED | |||||||
Hetchy Power | ||||||||
Transmission/Distribution | 32,415 | 37,652 | 33,852 | 44,502 | 68,827 | 236,322 | 453,570 | |
Streetlights | - | 3,815 | 3,815 | 3,815 | 3,815 | 19,075 | 34,335 | |
Treasure Island Capital Improvement | 4,333 | 1,483 | 2,733 | 1,483 | 1,483 | 6,020 | 17,533 | |
Renewable/Generation | 1,000 | 1,000 | 1,000 | 1,000 | 1,000 | 5,000 | 10,000 | |
Energy Efficiency | 1,000 | 886 | 1,000 | 1,000 | 1,000 | 5,000 | 9,886 | |
Hetchy Power Subtotal | 38,747 | 44,835 | 42,400 | 51,800 | 76,125 | 271,417 | 525,324 | |
Hetchy Water | ||||||||
Water Infrastructure | 33,733 | 65,850 | 46,373 | 43,457 | 18,657 | 62,826 | 270,896 | |
Power Infrastructure | 10,560 | 49,425 | 23,836 | 18,535 | 13,246 | 52,986 | 168,588 | |
Joint Projects - Water Infrastructure (45%) | 30,232 | 34,252 | 35,353 | 33,235 | 25,783 | 108,544 | 267,399 | |
Joint Projects - Power Infrastructure (55%) | 36,950 | 41,864 | 43,209 | 40,621 | 31,513 | 132,665 | 326,821 | |
Hetchy Water Subtotal | 111,474 | 191,391 | 148,771 | 135,848 | 89,200 | 357,022 | 1,033,705 | |
TOTAL | 150,222 | 236,226 | 191,171 | 187,647 | 165,324 | 628,439 | 1,559,029 | |
REVENUES | ||||||||
Revenue | 2,151 | 2,738 | 5,047 | 5,161 | 10,380 | 123,097 | 148,573 | |
Power Bonds | 81,571 | 131,201 | 101,865 | 103,145 | 107,891 | 320,723 | 846,395 | |
Water Bonds | 63,965 | 100,102 | 81,726 | 76,692 | 44,404 | 171,370 | 538,259 | |
Cap and Trade Auction Revenue | 535 | 886 | 1,233 | 1,350 | 1,350 | 6,749 | 12,102 | |
Low Carbon Fuel Standard | 2,000 | 1,300 | 1,300 | 1,300 | 1,300 | 6,500 | 13,700 | |
TOTAL | 150,222 | 236,226 | 191,171 | 187,647 | 165,324 | 628,439 | 1,559,029 | |
Total San Francisco Jobs/Year | 673 | 1,058 | 856 | 840 | 740 | 2,815 | 6,983 | |
SFPUC: CleanPowerSF | FY 2022 | FY 2023 | FY 2024 | FY 2025 | FY 2026 | FY 2027 - 2031 | Plan Total | |
SPENDING PLAN | ||||||||
Local Renewable Energy Program | 509 | 224 | 224 | 489 | 349 | 60,876 | 62,671 | |
CleanPower SF Customer Program | 1,924 | 1,249 | 1,199 | 1,149 | 1,324 | 6,245 | 13,090 | |
TOTAL | 2,433 | 1,473 | 1,423 | 1,638 | 1,673 | 67,121 | 75,761 | |
REVENUES | ||||||||
Revenue | 2,433 | 1,473 | 1,423 | 1,638 | 1,673 | 67,121 | 75,761 | |
TOTAL | 2,433 | 1,473 | 1,423 | 1,638 | 1,673 | 67,121 | 75,761 | |
Total San Francisco Jobs/Year | 11 | 7 | 6 | 7 | 7 | 301 | 339 |