New Infrastructure + Streets: Renewal Program

Renewal Program

The Plan proposes $1.3 billion in funding for Public Works renewal needs over the next 10 years, with $908 million coming from the General Fund, as shown in Chart 9.1. SFPUC renewal projects are not represented in this curve.

Chart 9.1
Chart 9.1

The General Fund streets and right-of-way renewal program includes street resurfacing, curb ramp inspection and replacement, median maintenance, plaza inspection and repair, sidewalk inspection and repair, street structure repair, and street tree planting, establishment, and maintenance. The street resurfacing program is by far the largest of these, with a planned investment of $897 million over the next 10 years. Of the other right-of-way programs, the sidewalk inspection and repair program and the street tree maintenance program are planned as fully funded; the remainder are planned to receive a proportional share of available funding.

The SFPUC’s renewal program includes sewer replacements, pump system rehabilitations, water storage upgrades, technology infrastructure improvements, and many other projects necessary to provide for San Francisco’s water, wastewater, and power needs. As noted above, SFPUC renewal projects are not included in the Service Area renewal curve as the General Fund does not fund the Enterprise Department's projects. For more information on SFPUC renewals, please see the narrative descriptions in the
following pages.

 

Project Name Description
PW – Curb Ramp Inspection 
and Replacement

This project complements the Curb Ramp Program (see Enhancement section below) with funding to maintain previously installed ramps.

The estimated cost for curb ramp inspection and replacement is $21.1 million over the next 10 years. Given anticipated funding constraints, the Plan allocates $11.7 million from the General Fund towards this need.

PW – Landscape Median Maintenance and Irrigation Repair

As San Francisco replaces more cement and concrete with green spaces, investment in maintaining these areas keeps them free of trash and promotes the health of plants. With more than 175 landscaped medians and open spaces across the city, irrigation systems require routine maintenance and repairs to prolong their useful lives and keep the landscaping in good condition.

The estimated cost for median maintenance is $160.0 million over the next 10 years. Given anticipated funding constraints, the Plan allocates $68.7 million from the General Fund towards this need, in addition to $36.0 million expected from the State.

PW – Plaza Inspection and 
Repair Program

Public Works is responsible for maintaining plazas throughout the City, including Blanken Bayshore, Embarcadero, Hallidie, Harvey Milk, Justin Herman, Mechanics, Mendell, Organ Pavilion, and United Nations Plazas. These plazas require annual inspection to determine the extent of any repairs that may be required.

The estimated cost for plaza inspection and repair is $11.4 million over the next 10 years. Given anticipated funding constraints, the Plan allocates $6.3 million from the General Fund towards this need.

PW – Sidewalk Improvements 
and Repair Program

Public Works maintains sidewalks in three ways. First, the Bureau of Urban Forestry maintains sidewalks around city-maintained street trees. Second, the Bureau of Street Use and Mapping executes the Sidewalk Inspection and Repair Program; its goal is to inspect and repair every block on a 25-year cycle. Finally, the Bureau of Street Mapping has a reactive program called the Accelerated Sidewalk Abatement Program, which inspects locations based on complaints and issues notices of violation to property owners to compel them to repair their dangerous sidewalks.

The estimated cost for sidewalk improvements and repair is $49.6 million over the next 10 years. The Plan recommends fully funding this need, with $19.3 million coming from the General Fund, and the remainder from other local sources.

PW – Street Resurfacing 
and Reconstruction

Public Works oversees the maintenance of 865 miles of streets. Without regular resurfacing treatments, a street could end up costing the City four times more over the course of its life cycle. San Francisco uses the industry standard rating scale called the Pavement Condition Index (PCI) to score its streets. Public Works’ goal is to achieve and maintain a PCI of 75, which is considered “good” condition.

The  estimated cost to achieve and maintain a PCI of 75 is $897 million over the next 10 years. The Plan recommends fully funding to achieve a PCI of 75 by 2025, with $543 million coming from the General Fund, and the remainder from a combination of federal, state, and other local sources.

PW – Street Structure Repair

The Capital Plan provides a strategy for the maintenance and renewal of 371 street structures including retaining walls, stairs, bridges, viaducts, tunnels, underpasses, and overpasses, plus numerous guardrails throughout the City. Work performed under this program includes general maintenance and major repairs of city street structures to maintain safety, proper operations of moveable bridges, and minimize long-term renewal costs. For this Plan, two major projects in this category include the Islais Creek and 4th Street bridges.

The estimated cost for the Islais Creek Bridge project is $102.0 million, with $11.7 million being funded by the General Fund, and $90.3  million from a Federal grant. The estimated cost for the 4th Street Bridge project is $22.6 million, with $2.6 million being funded by the General Fund, and $20.0 million from a Federal grant.

The estimated cost for other street structure repair is $70.2 million over the next 10 years. Given anticipated funding constraints, the Plan allocates $38.9 million from the General Fund towards this need.

PW – Street Tree Maintenance 
and Sidewalk Repair

Public Works is responsible for maintaining approximately 125,000 street trees. Proposition E of the November 2016 ballot set aside annual funding towards this need, and Public Works will have the resources to maintain street trees on an average three-to-five-year cycle, inspect all street trees annually, and make sidewalk repairs on a similar cycle.

The estimated cost for street tree maintenance and related sidewalk repair is $220.1 million over the next 10 years, fully funded by the General Fund through Proposition E.

SFPUC Hetch Hetchy – 
Water Infrastructure

The Water Infrastructure Renewal and Replacement program will include concept, development, design, and upgrades for operating, managing, and maintaining the Hetchy Water Infrastructure. In general, this includes water facilities from Hetch Hetchy Reservoir to Alameda East. The new and upgraded systems will have increased coverage, capacity or reliability, or improve employee safety and/or operating efficiency. The Hetchy water renewal program includes continued rehabilitation to the San Joaquin Pipeline. New projects include the San Joaquin Pipeline Valve and Safety Improvement Project to extend the useful life and safety of Hetchy Water assets and the Priest-Moccasin Water Transmission Line Project to build a new pipeline system to bypass the Moccasin Powerhouse.

The cost of SFPUC’s Hetch Hetchy – Water Infrastructure renewal and replacement projects is approximately $353.4 million through FY2029.

SFPUC Hetch Hetchy – 
Power Infrastructure

Many Hetchy Power systems, facilities, and equipment have reached their end of their life expectancy. Projects for Hetchy Powerhouses include upgrades to the powerhouse protection, control and monitoring systems, and equipment replacement and upgrades. The Capital Plan also includes rehabilitation of transmission lines and distribution systems, reliability projects that address North American Electric Reliability (NERC) requirements. Typical projects include replacement of insulators, switches, tower infrastructure, grounding, and protection, as well as regulatory projects. Two new projects are associated with dams and reservoirs for water storage and power generation: the Priest Reservoir Condition Assessment Project to assess updating the stability of the dam and the Cherry Elenore Pump Project to replace the pump at the reservoirs and upgrading systems.

The cost of SFPUC’s Hetch Hetchy – Power Infrastructure renewal and replacement projects is approximately $130.3 million through FY2029.

SFPUC Hetch Hetchy – 
Water and Power Joint Infrastructure

There are assorted SFPUC projects that will support multiple enterprises. Communications projects provide upgrades of the communication systems elements to maintain pace with the changes in technology, and to maintain overall system reliability. Upgrades to dams and reservoirs will meet the Water Levels of Service and Power Operational Objectives; funding is included for O’Shaughnessy Dam to improve the access and upgrade bulkhead, gate valves, and drum gates. The Mountain Tunnel will address deterioration in the concrete lining of the tunnel for continued reliability with a project plan more than $400 million less than anticipated in the last Capital Plan. Roads and bridges will make replacements and improvements as recommended in condition assessment reports and road improvements program to keep up access to Hetch Hetchy Water and Power facilities. Tunnels projects include the Canyon Tunnel-Hetchy Adit Rehabilitation to install a new reinforced concrete plug downstream of the existing plug. The new plug can be built while the Canyon Tunnel remains in service. Utilities projects will maintain the power distribution system in a state of good repair consistent with utility best practices to ensure 24/7 power.

The cost of SFPUC’s Hetch Hetchy Water and Power – Joint Infrastructure renewal and replacement projects is approximately $383.7 million through FY2029. These assets are jointly funded by Water (45%) and Power (55%) sources.

SFPUC Wastewater – Collection System Spot Sewer Repair Project

This project provides as-needed contingency-based repairs of existing sewer pipes for a city block or less in length. Current funding levels are projected to repair approximately 700 individual spot sewer locations per fiscal year to meet the targeted levels of service goals. It is anticipated that this base rate of spot repair will continue for the next several years and would ultimately decrease.

The cost of SFPUC’s Collection System Spot Sewer Repair Project is approximately $184.8 million through FY2029.

SFPUC Wastewater – Condition Assessment Project

There are more than 80 miles of major sewers that have been in service for 100 years or more and are at the end of their useful life. This project will confirm needs and provide recommendations for replacement or rehabilitation of major sewers as part of the Sewer System Improvement Program.

The cost of SFPUC’s Condition Assessment Project is approximately $41.9 million through FY2029.

SFPUC Wastewater – 
Salt Water Intrusion

Salt water corrodes the pipes and concrete of the sewer system. If it reaches the treatment plant in large quantities, it can harm or kill the biological secondary treatment process, cause discharge permit violations, and harm receiving water quality. Salt Water Intrusion projects reduce salt water intrusion into the sewer system with sewer pipeline joint sealing work.

The cost of SFPUC’s Wastewater Salt Water Intrusion project is approximately $9.4 million through FY2029.  

SFPUC Wastewater – Sewer Replacement/Improvement Program

Failure of the collection system would reduce the City’s ability to handle and dispose of wastewater and stormwater, which could lead to public health, safety, and environmental risks and non-compliance with the State of California’s discharge permit. This program maintains the existing functionality of the sewage collection system and includes planned and emergency repairs and replacement of structurally inadequate sewers. This program allows for the renewal and replacement of approximately 15 miles of sewer per year.

The cost of SFPUC’s Sewer Replacement/Improvement Program is approximately $801.3 million through FY2029.

SFPUC Wastewater – 
Treatment Plants

The Treatment Plant Improvement program helps maintain the capacity and reliable performance of the Wastewater treatment facilities owned and operated by the Wastewater Enterprise. This is a continuing annual program to extend the useful life of Wastewater treatment assets including transport boxes, discharge structures, pump stations, force mains, tunnels, and treatment plants. The projects are prioritized based upon regulatory compliance, condition assessments, operations staff recommendations, and level of service goals, which were formally adopted as part of the SSIP.

The cost of SFPUC’s Treatment Plants is approximately $303.7 million through FY2029.

SFPUC Water – Local Buildings and Grounds Improvements

Capital improvements at City Distribution Division (CDD) facilities and structures are needed. Projects include a new fueling station, yard improvements to address health and safety issues and security, a comprehensive arc flash and electrical hazard study, and construction of a seismically reliable building for CDD’s communications and control systems. Additional funding is included for full replacement of the Newcome Yard facilities to address life safety standards for seismic events, building code requirements, and facilities past useful life.

The cost of SFPUC Water’s Local Buildings and Grounds Improvements is approximately $40.2 million through FY2029.

SFPUC Water – Local Water Conveyance/Distribution System

This program installs, replaces, and renews distribution system pipelines and service connections for the 1,230 miles of drinking water mains in San Francisco to meet customer level of service goals for uninterrupted service. The increased investment is needed to improve the annual replacement rate to 15 miles per year to minimize main breaks. Improvements include replacement, rehabilitation, re-lining, and cathodic protection of all pipe categories to extend or renew pipeline useful life. Additional projects include the Automated Water Meter Program, New Services Connection Program, and Town of Sunol Pipeline projects.

The cost of SFPUC’s Local Water Conveyance/Distribution System is approximately $617.8 million through FY2029.

SFPUC Water – Local Pump Stations

The SFPUC’s 12 major water pump stations and seven hydropneumatic tanks that boost pressure within the San Francisco distribution system need ongoing renewal and rehabilitation. This program includes funding to fully rebuild the McLaren Park pump station.

The cost of SFPUC Water’s Local Pump Stations is approximately $20.3 million through FY2029.

SFPUC Water – Local Recycled Water Projects

Projects in this program include the San Francisco Westside Recycled Water Project, funding new facilities to generate and deliver 2 MGD of recycled water for irrigation use in the western end of San Francisco. The project includes a new recycled water treatment facility consisting of membrane filtration, reverse osmosis, and ultraviolet light disinfection; a 1.1-million-gallon storage reservoir; distribution pumping facilities; and five to six miles of new pipelines.

The cost of SFPUC Water’s Local Recycled Water Projects is approximately $1.2 million through FY2029.

SFPUC Water – Local Systems Monitoring and Controls

This program delivers improvements to facilities that control and monitor San Francisco’s water distribution system. Facilities include enhancements to the System Control and Data Acquisition (SCADA) for remote monitoring of pressure, flow, and valve position status at key locations throughout the distribution system. This program will also fund installation of fiber optic communications to critical facilities and security installations not completed under the Water System Improvement Program (WSIP).

The cost of SFPUC Water’s Local Systems Monitoring and Controls is approximately $2.5 million through FY2029.

SFPUC Water – Local Tanks/Reservoir Improvements

This program provides long-term funding for renewal and rehabilitation of water storage reservoirs and tanks within the San Francisco Distribution System. Projects include seismic upgrades to the College Hill Reservoir Outlet, Merced Manor concrete wall and roof reinforcements, and Lombard Reservoir Geotechnical Improvements to stabilize the northeast slope of the reservoir and mitigate potential failure during major rain events.

The cost of SFPUC Water’s Local Tanks/Reservoir Improvements is approximately $5.6 million through FY2029.

SFPUC Water – 
Local Water Supply Projects

This program includes planning for local water diversification to explore alternative methods for expanding local water sources. Such sources include the Eastside Water Purification Project and Innovations for San Francisco ratepayers that highlight innovative water supplies and technologies.

The cost of SFPUC Water’s Local Water Supply Projects is approximately $5.5 million through FY2029.

SFPUC Water – Regional Buildings and Grounds Programs

This program provides funding for major improvements to the Sunol and Millbrae Yards. Sunol Yard improvements include LEED replacement facilities for maintenance shops and equipment storage, a new fueling center and administration building, re-surfacing of the yard, and demolition of six dilapidated structures. The project includes funding for the Sunol Watershed Center that includes exhibits, classrooms, event space, outdoor picnic and play areas, trails, and gardens representing the watershed. Millbrae Yard improvements include a new administration building to consolidate the Water and Wastewater laboratory, maintenance shop, and equipment storage, demolition of a large unused abandoned building, a new parking lot, and a new vehicle wash site. The upgrades address occupational safety, reliability, and functional regulatory compliance.

The cost of SFPUC Water’s Regional Buildings and Grounds Programs is approximately $61.1 million through FY2029.

SFPUC Water – 
Regional Communications and Monitoring Program

This project will provide much needed redundant emergency communications capability and increased bandwidth for security data transfer. Specifically, it will build a microwave backbone to link the entire SFPUC regional water system from the Hetch Hetchy Dam site in Yosemite to the rest of the SFPUC sites (San Francisco, San Mateo, Santa Clara, and Alameda counties).

The cost of SFPUC Water’s Regional Communications and Monitoring Program is approximately $11.1 million through FY2029.

SFPUC Water – Regional Water Supply and Storage Program

This program includes upgrades to structures to meet State Division of Safety of Dams requirements including geotechnical work, installation of monitoring systems, and a regional desalination project. The automated data acquisition system in the monitoring system will provide timely, accurate data related to inspections at various dams. This program will also include Regional Water Diversification Projects to explore alternative methods to expand regional water sources including a Regional Desalination Project, Indirect Potable Reuse Project, and Los Vaqueros expansion.

The program also includes the Daly City Recycled Water Expansion Project to provide 3.4 MGD of recycled water to customers of the Regional Water System and help offset groundwater pumping in the Westside Basin.

The cost of SFPUC Water’s Regional Water Supply and Storage Program is approximately $220.5 million through FY2029.

SFPUC Water – Regional Water Transmission Program

This program will provide upgrades to the Transmission System including pipeline inspection and repairs, valve replacements, metering upgrades, corrosion protection, and pump station and vault upgrades. As part of the pipeline improvement program, funding is included to monitor, strengthen, and replace older pipeline to achieve higher level performance and reliability. Included is funding to replace or slip line up to 10 miles of pipeline in densely populated areas.

The cost of SFPUC Water’s Regional Water Transmission Program System is approximately $289.9 million through FY2029.

SFPUC Water – Regional Water Treatment Program

This program includes major upgrades to the Sunol Valley and Harry Tracy Water Treatment Plants. Projects are identified through condition assessments, operations staff review, level of service and feasibility studies, and alternative analysis at each plant. Projects include upgrades of chemical dosage, flow monitoring, valve and pump replacement, and chemical handling upgrades. New projects include installation of ozone generators and power activate carbine units to address taste and odor issues at the Sunol Valley Plant.

The cost of SFPUC Water’s Regional Water Treatment Program is approximately $136.1 million through FY2029.

SFPUC Water – Regional Watersheds and Land Management

This program supports projects that improve and/or protect the water quality and/or ecological resources impacted by the siting and operation of SFPUC facilities. Projects include the repair, replacement, maintenance, or construction of roads, fences, or trails, the acquisition of easements and/or fee title of properties, and other ecosystem restoration or public access, recreation, and education projects. The Long-Term Monitoring and Permit Program provides resources to comply with terms and conditions in state and federal permits associated with construction and operation and maintenance of the PUC Water System.

The cost of SFPUC Water’s Regional Watersheds and Land Management is approximately $44.6 million through FY2029.

SFPUC Water – Emergency Firefighting Water System

The Emergency Firefighting Water System (EFWS) delivers high-pressure water necessary to fight large fires and is being jointly developed by the SFPUC and San Francisco Fire Department. SFPUC funds are planned to support the design and construction of earthquake resistant ductile pipeline to improve fire water and potable water supply reliability in the Sunset and Richmond neighborhoods.

The SFPUC has planned $53.8 million from Water Revenue Bonds over the next five years to support western EFWS water supply and pipeline projects. The ESER G.O. Bond is the primary source of funding for EFWS. For additional information on EFWS, including the ESER Bond Program and strategic direction about work on the west side, please see the Public Safety chapter of this Plan.

Infrastructure + Streets: Renewal Program

Renewal Program

The Plan proposes $1.3 billion in funding for Public Works renewal needs over the next 10 years, with $908 million coming from the General Fund, as shown in Chart 9.1. SFPUC renewal projects are not represented in this curve.

Chart 9.1
Chart 9.1

The General Fund streets and right-of-way renewal program includes street resurfacing, curb ramp inspection and replacement, median maintenance, plaza inspection and repair, sidewalk inspection and repair, street structure repair, and street tree planting, establishment, and maintenance. 

The PUC’s renewal program includes sewer replacements, pump system rehabilitations, water storage upgrades, technology infrastructure improvements, and many other projects necessary to provide for San Francisco’s water, wastewater, and power needs. As with Enterprise departments covered in other chapters, PUC renewal projects are not included in the Service Area renewal curve. For more information on these projects, please see the narrative descriptions included in the following table.

Project Name Description
PW – Street Resurfacing and Reconstruction

Public Works oversees the maintenance of 865 miles of streets. Without regular resurfacing treatments, a street could end up costing the City four times more over the course of its life cycle. As approved by city officials and voters, Public Works’ goal is to achieve and maintain a Pavement Condition Index score (PCI) of 70. This target will take streets from the “at-risk” to a more cost-effective “good”.

 

The estimated cost to achieve and maintain a PCI of 70 is $816 million over the next 10 years. The Plan recommends fully funding this need, with $693 million coming from the General Fund, and the remainder from a combination of federal, state, and other local sources.

PW – Curb Ramp Inspection and Replacement

Title II of the Americans with Disabilities Act requires local entities to develop a transition plan specifically for curb ramps. The City is committed to improving curb ramps and providing accessible paths of travel for people with disabilities. This project complements the installation of new ramps (see the Enhancements section below for additional details) by ensuring sufficient funds for maintaining previously installed ramps.

 

The estimated cost for curb ramp inspection and replacement is $16 million over the next 10 years. Given funding constraints, the Plan allocates $9 million from the General Fund towards this need.

PW – Median Maintenance

As the City converts more paved areas into green space, Public Works needs capacity to maintain these areas to ensure that the investments last and that medians and other landscape spaces are kept in great condition. There are irrigation systems at 67 landscaped medians across the City.

 

The estimated cost for median maintenance is $147 million over the next 10 years. Given funding constraints, the Plan allocates $57 million from the General Fund towards this need, in addition to $50 million expected from the State.

PW – Plaza Inspection and Repair Program

Public Works is responsible for maintaining fourteen plazas throughout the City, including: Blanken Bayshore, Embarcadero, Hallidie, Harvey Milk, Justin Herman, Mechanics, Mendell, Organ, United Nations, Civic Center, Tutubi, McCoppin Hub, Bartlett, and Corbett Community Garden. These plazas require annual inspection to determine the extent of any repairs that may be required.

 

The estimated cost for plaza inspection and repair is $22 million over the next 10 years. Given funding constraints, the Plan allocates $13 million from the General Fund towards this need.

PW – Sidewalk Improvements and Repair Program

Public Works maintains sidewalks in three ways. First, the Bureau of Urban Forestry maintains sidewalks around city-maintained street trees. Second, the Bureau of Street Use & Mapping executes the Sidewalk Inspection and Repair Program; its goal is to inspect and repair every block on a 25-year cycle. Finally, Bureau of Street Mapping also has a reactive program called the Accelerated Sidewalk Abatement Program, which inspects locations based on complaints and issues notices of violation to property owners in order to compel them to repair their dangerous sidewalks.

 

The estimated cost for sidewalk improvements and repair is $37 million over the next 10 years. The Plan fully funds this need, with $14 million coming from the General Fund, and the remainder from the State, and other local sources.

PW – Street Structure Repair

The Capital Plan provides a strategy for the maintenance and renewal of 364 street structures including retaining walls, stairs, bridges, viaducts, tunnels, underpasses and overpasses, plus numerous guardrails throughout the City. Work performed under this program includes general maintenance and major repairs of city street structures to maintain safety, proper operations of moveable bridges, and minimize long-term renewal costs. For this Plan, two major projects in this category include the Islais Creek and 4th Street bridges.

 

The estimated cost for the Islais Creek Bridge project is $45 million, with $5.4 million being funded by the General Fund, and $39 million from a Federal grant. The estimated cost for the 4th Street Bridge project is $22 million, with $2.6 million being funded by the General Fund, and $20 million from a Federal grant.
The estimated cost for other street structure repair is $67 million over the next 10 years. Given funding constraints, the Plan allocates $40 million from the General Fund towards this need.

PW – Street Tree Planting, Establishment, and Maintenance

By FY2018, Public Works will be responsible for maintaining approximately 121,000 street trees. Public Works will have the resources to maintain street trees on an average three-to-five-year cycle, inspect all street trees annually, and make sidewalk repairs on a similar cycle. Additionally, the City anticipates replacing approximately four percent of trees each year as a result of typical tree mortality, disease, or vandalism.

 

The estimated cost for street tree planting, establishment, and maintenance is $250.5 million over the next 10 years. The Plan fully funds this need, with $219.9 million from the General Fund, in addition to $30.6 million expected from State and other local sources.

SFPUC Hetch Hetchy Water and Power – Mountain Tunnel Rehabilitation Project Mountain Tunnel was constructed between 1917 and 1925, and has provided reliable water conveyance for nearly 90 years. Deterioration in the concrete lining of the tunnel has increased in recent decades, and the tunnel is in need of rehabilitation and/or replacement to ensure continued reliability.
SFPUC Hetch Hetchy Water and Power Projects – Power Infrastructure

Many Hetchy Power infrastructure, facilities, and equipment have reached their end of their life expectancy. The Capital Plan provides funding for various generation renewal and replacement projects at the Holm, Kirkwood and Moccasin Powerhouses. These projects include upgrades to the powerhouse protection, control, monitoring systems, equipment replacement and upgrades.

 

The Capital Plan also includes rehabilitation of transmission lines and distribution systems, which consist of reliability projects to address regulatory requirements. Typical projects in this program include replacement of insulators, switches, tower infrastructure, grounding and protection. Distribution system projects include upgrades to distribution lines, dry transformers, distribution substations; disconnect switches, breakers, protection, and metering.

SFPUC Hetch Hetchy Water and Power – Water Infrastructure The San Joaquin Pipelines convey water from the Foothill Tunnel to the Coast Range Tunnel and vary in age from 45 to almost 80 years. Rehabilitation is intended to extend the life of the assets to about 2030 before requiring replacement.
SFPUC Wastewater – Collection System Spot Sewer Repair Project This project provides as-needed contingency-based repairs of existing sewer pipes for a city block or less in length. Current funding levels are projected to repair approximately 700 individual spot sewer locations per fiscal year, to meet the targeted levels of service goals. It is anticipated that this base rate of spot repair will continue for the next several years and would ultimately decrease as the overall program continues to be implemented.
SFPUC Wastewater – Condition Assessment Project There are more than 80 miles of major sewers that have been in service for 100 years or more and are at the end of their useful life. This project will confirm needs and provide recommendations for replacement or rehabilitation of major sewers through the Sewer System Improvement Program.
SFPUC Wastewater – Salt Water Intrusion Salt water corrodes the pipes and concrete of the system. If it reaches the treatment plant in large quantities, it can harm or kill the biological secondary treatment process, cause discharge permit violations and harm receiving water quality. The Salt Water Intrusion projects will reduce salt water intrusion into the sewer system. Projects in this area will consist of sewer pipeline joint sealing work.
SFPUC Wastewater – Sewer Replacement/Improvement Program

Failure of the collection system will reduce the City’s ability to handle and dispose of wastewater and stormwater which can lead to public health, safety and environmental risks and non-compliance with the State of California’s discharge permit. This program maintains the existing functionality of the sewage collection system and includes planned and emergency repairs and replacement of structurally inadequate sewers.


The estimated annual cost for sewer replacement beginning in FY2018 is approximately $60 million and increases to $88 million by FY2027 allowing the renewal and replacement of approximately 15 miles of sewer per year.

SFPUC Wastewater – Treatment Plants This renewal program seeks to extend the useful life of treatment facility assets throughout San Francisco by helping to maintain their treatment capacity, process performance, and ensure compliance with regulatory requirements.
SFPUC Water – Emergency Firefighting Water System

The Emergency Firefighting Water System (EFWS) will increase the safety response capacity of the Fire Department following a major earthquake and during multiple-alarm fires from other causes. This project includes improvements to or expansion of EFWS pipelines, tunnels, and physical plant.

 

For project financial information, please see the Public Safety chapter of this Plan.

SFPUC Water – Local Buildings & Grounds Improvements This project will provide funding for capital improvements at City Distribution Division facilities and structures. Projects in this area include a new fueling station, yard improvements to address health and safety issues and security, a comprehensive arc flash and electrical hazard study and construction of a seismically reliable building for City Distribution Division’s communications and control systems.
SFPUC Water – Local Water Conveyance/Distribution System Currently, 16% of the SFPUC’s 1,230 miles of mains exceed their typical 100-year useful life. This project includes funding to install, replace and renew distribution system pipelines and service connections for drinking water mains in San Francisco and meet customer level of service goals for uninterrupted service. The increased investment is needed to improve annual replacement rate to 15 miles per year to minimize main breaks due to aging infrastructure resulting in fewer service disruptions, property damage and need for emergency repairs.
SFPUC Water – Local Water System Improvement Program (WSIP) Augmentation This project includes a new recycled water treatment facility that will provide irrigation water to Golden Gate Park, Lincoln Park, and the SF Zoo. It includes additional capacity to serve potential future customers such as the Presidio Golf Course.
SFPUC Water – Pump Stations This project provides long-term funding for renewal and rehabilitation of 12 major water pump stations and seven hydropneumatic tanks that boost pressure within the San Francisco distribution system, including the McLaren Park and Bay Bridge pump stations.
SFPUC Water – Regional Buildings & Grounds Programs Sunol Yard improvements include replacement structures with LEED facilities for maintenance shops and equipment storage, new fueling center and administration building, re-surfacing of yard, and demolition of six dilapidated structures. Millbrae Yard improvements include a new administration building to consolidate the Water and Wastewater laboratory, maintenance shop, and equipment storage, demolition of a large unused abandoned building, new parking lot, and new vehicle wash site.
SFPUC Water – Regional Communications & Monitoring Program The objective of this project is to build a microwave radio backbone for communications and security systems, including video surveillance, remote gate locks, and audio monitoring, across the entire SFPUC regional system. This will enhance SFPUC emergency response, security, and regional interoperability.
SFPUC Water – Regional Water Supply & Storage Program The California State Division of Safety of Dams requires upgrades to structures, including geotechnical work and installation of monitoring systems. The automated data acquisition system, part of the monitoring system, will provide timely, accurate data related to inspections at various dams.
SFPUC Water – Regional Water Treatment Program In addition to maintaining compliance with permits, improvements to regional treatment plants are expected to achieve higher levels of reliable performance for extended periods.
SFPUC Water – Regional Water Transmission Program

This program will provide upgrades to the Transmission System including pipeline inspection and repairs, valve replacements, metering upgrades, corrosion protection to extend the useful life of the pipelines, pump station upgrades and vault upgrades.

 

Included is $157 million funding for Pipeline Improvement Program over the next 10 years to replace or slip-line up to 10 miles of pipelines in densely populated areas to improve operational reliability and reduce liability.

SFPUC Water – Regional Watersheds & Land Management This program supports projects that improve and protect the water quality and ecological resources impacted by the siting and operation of PUC facilities. These projects include the repair, replacement, maintenance, or construction of roads, fences, or trails, the acquisition of easements and/or fee title of properties, and other ecosystem restoration or public access, recreation, and education projects.
SFPUC Water – Regional Water System Improvement Program (WSIP) Augmentation Additional funding at Calaveras Dam and the Alameda Creek Diversion Dam is needed for unanticipated subsurface conditions and localized slope stability which will result in increases in rock support, shotcrete, and shale disposal work. The revised baseline schedule will still allow the dam embankment to be complete by fall 2018, which will allow filling of the reservoir to begin in the fall/winter 2018-19 as planned.
SFPUC Water – System Monitoring and Control The System Control and Data Acquisition (SCADA) provides remote monitoring of pressure, flow, and valve position status at key locations throughout the distribution system. This project provides improvements to SCADA and to facilities that control and monitor San Francisco’s water distribution system. This program will also install fiber optic communications to critical facilities and security installations not completed under WSIP.
SFPUC Water – Water Storage Facilities The PUC maintains 10 major water storage reservoirs and six storage tanks that range in age from 50 to 120 years old. The College Hill Reservoir supplies much of the eastern and northern areas of San Francisco, including Zuckerberg San Francisco General Hospital, the City’s trauma center. This project provides long-term funding for the renewal and rehabilitation of these reservoirs and tanks. Planning evaluation and geotechnical review were conducted and recommend that the outlet structure be replaced with a new 48-inch diameter steel pipeline with outlet valve facilities.

Infrastructure + Streets: Overview

Overview

Programs addressed in this chapter are delivered by the San Francisco Public Works and the San Francisco Public Utilities Commission. Among the key programs implemented by Public Works are Street Resurfacing, Sidewalk Repair, and Street Tree Planting. SFPUC provides San Francisco with water, power, and wastewater systems, with multi-billion dollar programs designed to prolong the life of these assets. Together, these two agencies provide tangible results that affect the lives of each and every San Franciscan.

Recently Completed Taraval Streetscape Project
Recently Completed Taraval Streetscape Project
Twin Peaks Reservior
Twin Peaks Reservoir

Public Works Streets and Rights-of-Way

The City has been able to make significant improvements when combining proceeds from the Road Repaving and Street Safety 2011 Bond Program with existing revenue sources for streets and right-of-way. The third and final bond sale was completed in the spring of 2016, rounding out the $248 million program dedicated to street resurfacing, streetscape, and traffic signal upgrade projects. 

In order to continue to improve streets and public right-of-way assets, the Plan recommends pursuit of dedicated long-term funding sources for street resurfacing as the General Fund lacks capacity to fully meet these needs. 

Since the last Capital Plan, the City has committed to Vision Zero with a goal of zero traffic fatalities and critical injuries in San Francisco by 2024. San Francisco’s expenditures in streets and right-of-way infrastructure improve safety in myriad ways. Roadway repaving creates a smoother surface and renews street and crosswalk markings, which improves the safety of drivers, bicyclists, and people in crosswalks. Additionally, the City continues to reaffirm our commitment to safe and accessible paths of travel for people with disabilities by making capital improvements to curb ramps, sidewalks, street crossings, and roadways across the City.

Public Utilities Commission

The San Francisco Public Utilities Commission (SFPUC) provides and distributes water to 2.6 million customers, treats wastewater, and supplies electric power to operate Muni streetcars and electric buses, street and traffic lights, and municipal buildings. The SFPUC includes three utility enterprises: Water, Wastewater, and Power. 

The Water Enterprise consists of over 389 miles of pipeline, over 74 miles of tunnels, 11 reservoirs, five pump stations, and three water treatment plants located outside of the City (the “Regional Water System”) and over 1,235 miles of pipeline, 11 reservoirs, eight storage tanks, 22 pump stations, eight hydropneumatic stations and 17 chlorination stations located within the city limit of the City (the “In-City Distribution System”). 

The Water Enterprise is responsible for the distribution of high quality water to its customer in San Francisco and other Bay Area communities. Hetch Hetchy wastershed, located in Yosemite National Park, provides approximately 85% of San Francisco’s total water needs, with the remaining 15% produced by the Alameda and Peninsula watersheds. The drinking water provided is among the purest in the world; the system for delivering that water is almost entirely gravity fed, requiring almost no fossil fuel consumption to move water from the mountains to your tap. Hetchy Water operates, maintains, and improves water and power facilities, smaller dams and reservoirs, water transmission systems, power generation facilities, and power transmission assets. 

The Wastewater Enterprise operates and maintains the City's water pollution control plants, pumping stations, and collection system in order to protect public health and the environment. The Wastewater Enterprise maintains the 900-mile long combined sewer system and 27 pump stations that collect sewage and storm water, moving wastewater to treatment plants for eventual discharge into the San Francisco Bay and the Pacific Ocean. The SFPUC is undertaking a Sewer System Improvement Program (SSIP) to modernize its systems and help meet its Levels of Service goals. The SSIP is expected to take place over the next 20 years. 

The Power Enterprise is responsible for providing reliable, clean, high-quality electric energy to the City. The Power Enterprise’s 100% GHG-free electric supply portfolio consists of hydroelectric power from three power plants in the Sierra Nevada mountains, solar power generated at SFPUC and other City facilities, and bio-methane power produced at SFPUC wastewater treatment facilities.

Water System Facilities Improvements
Water System Facilities Improvements

 

2022 - Health + Human Services: Financial Summary

09. Health and Human Services

Financial Summary

Programs / Projects
(Dollars in Thousands)
FY 2022 FY 2023 FY 2024 FY 2025 FY 2026 FY 2027 - 2031 Plan Total  
State of good repair renewal - Need 34,422 35,627 37,409 39,279 41,243 239,288 427,269  
                 
SPENDING PLAN               DEFERRED
State of good repair renewal - Proposed Uses 1,723 1,946 2,904 8,524 10,445 93,362 118,903 321,125
Mental Health SF 207,000 - - - - - 207,000 -
Enhancements 250,000 256,500 - - - - 506,500 340,128
TOTAL 458,723 258,446 2,904 8,524 10,445 93,362 832,403 661,253
                 
REVENUES                
General Fund 1,723 1,946 2,904 8,524 10,445 93,362 118,903  
Public Health Bond 2023 - 186,500 - - - - 186,500  
Health and Recovery Bond 2020 207,000 - - - - - 207,000  
Certificates of Participation - 70,000 - - - - 70,000  
Developer Funded 250,000 - - - - - 250,000  
TOTAL 458,723 258,446 2,904 8,524 10,445 93,362 832,403  
Total San Francisco Jobs/Year 2,055 1,158 13 38 47 418 3,728  

New Health + Human Services: Financial Summary

Financial Summary
PROGRAMS/PROJECTS
(Dollars in Thousands)
FY
2020
FY
2021
FY
2022
FY
2023
FY
2024
FY 2025 - 2029 Plan Total  
State of Good Repair Renewal - Need 25,875 27,169 28,527 29,953 31,451 182,477 325,452  
                 
SPENDING PLAN                
State of Good Repair Renewal - Proposed Uses 9,526 10,960 12,810 14,040 15,866 117,901 181,103 131,008
Enhancements 200,000 - - 220,000 - - 420,000 1,886
HOPE SF 2,305 2,185 1,825 1,825 1,825 5,188 15,152 -
TOTAL 211,831 13,145 14,635 235,864 17,691 123,089 616,255 132,894
 
REVENUES                
General Fund 9,526 10,960 12,810 14,040 15,866 117,901 181,103  
Public Health Bond 2023 - - - 200,000 - - 220,000  
Developer Funded 200,000 - - - - - 200,000  
HOPE SF Capital Fund Program 2,305 2,185 1,825 1,825 1,825 5,188 15,152  
TOTAL 211,831 13,145 14,635 235,864 17,691 123,089 616,255  
Total San Francisco Jobs/Year 1,256 78 87 1,399 105 730 3,654  

Health + Human Services: Financial Summary

Financial Summary
PROGRAMS/PROJECTS (Dollars in Thousands) FY
2018
FY
2019
FY
2020
FY
2021
FY
2022
FY 2023 -
2027
Plan Total Backlog
State of Good Repair Renewal - Need 26,096 27,401 28,771 30,210 31,720 184,038 328,237  
                 
SPENDING PLAN                
State of Good Repair Renewal - Uses 12,053 14,119 15,168 16,286 18,117 120,123 195,866 175,657
Enhancements 206,800 219,564 - - 300,000 - 726,364 30,154
HOPE SF 2,948 1,498 1,269 1,122 1,028 6,000 13,864 8,488
TOTAL 221,800 235,181 16,437 17,408 319,145 126,123 936,095 214,300
 
REVENUES                
General Fund 12,053 14,119 15,168 16,286 18,117 120,123 195,866  
General Fund - Enhancement 200 250 - - - - 450  
Capital Planning Fund 2,000 - - - - - 2,000  
Public Health and Safety Bond 2016 20,000 125,514 - - - - 145,514  
Public Health Bond 2022 - - - - 300,000 - 300,000  
Certificates of Participation 90,800 - - - - - 90,800  
Developer Funded 93,800 93,800 - - - - 187,600  
Other Local Sources 1,595 1,499 1,122 1,122 1,029 5,000 11,367  
TOTAL 220,447 235,182 16,290 17,408 319,145 125,123 933,597  
Total San Francisco Jobs/Year 1,841 1,964 136 145 2,665 1,045 6,751  
 
Annual Surplus (Deficit) (1,353) 1 (147) - - (1,000) (2,498)  
Cumulative Surplus (Deficit) (1,353) (1,352) (1,499) (1,498) (1,498) (1,498)    

2022 - Health + Human Services: Emerging Projects

09. Health and Human Services

Emerging Projects

Project Name Description
DPH – ZSFG Campus Security Enhancements  The ZSFG campus has many public entrances and doorways that are either mechanically keyed or have a non-networked combination badge card reader. In order to improve safety and security, this project would include installation of door card readers that are connected to the campus security network program. This project would also add security enhancements, including loading dock security at Building 5, campus perimeter fence repairs, door alarm hardware replacement, campus security duress button installations, and an ambulance bay security gate.
DPH – Aging Infrastructure Projects Outstanding DPH needs include seismically-deficient Buildings 1, 10, 20, 30, 40, and 100 at ZSFG; renovating remaining unoccupied buildings at LHH; addressing long outstanding needs at neighborhood clinics not covered by currently planned funding sources; and needs related to the Population Health Division City Clinic.
DPH – 101 Grove Retrofit  Once Department of Public Health staff exit the offices at 101 Grove Street, the City will have to decide how to activate the building. The monumental Beaux Arts 101 Grove is contributory to the Civic Center Historic District and not eligible for replacement. The City will evaluate whether a sale, public-private partnership, or City-driven retrofit project will make for the best use of the space and funds required. No preliminary costing for any of these scenarios has been developed.
HSH – Accessibility and Barrier Removal MOD has identified several accessibility and barrier removal needs at the City’s homeless shelters. A significant number of residents with disabilities need to access these systems, especially when elevators and restroom facilities are unusable because of accessibility barriers. Over the past five years, MOD has received several complaints related to accessibility deficiencies in the shelter system.  The most common complaints cited lack of a functioning elevator, need for code compliant electrical outlets, accessible restroom features, better front door access (e.g., request for power operators), and difficulty with caregiver access to the shelters.
HSH – New Family Shelter This project will provide a replacement emergency shelter for families experiencing homelessness in a permanent site with full shelter amenities. The City's existing family shelter in the Western Addition site was closed due to COVID-19. While the facility accommodated up to 30 families, it lacked showers and other basic amenities. HSH will need to conduct a site search and feasibility assessment with assistance from the Department of Real Estate and Public Works in order to secure a site.
HSH – Shelter Seismic Retrofits San Francisco continually reviews and assesses the seismic risks throughout our portfolio of public facilities. Similar to Chinatown Health Clinic mentioned above, all three of the city-owned shelters have a Seismic Hazard Rating of 4, which means suffer significant damage in a large earthquake and will likely be red-tagged or taken out of operation in a smaller earthquake. As such, developing plans and identifying funds to retrofit these shelters is a high priority. HSH is coordinating with Real Estate, Public Works, and the Office of Resilience and Capital Planning to develop a master plan to address seismic deficiencies at the shelters, without diminishing the number of shelter beds available to people experiencing homelessness in San Francisco.

 

New Health + Human Services: Emerging Projects

Emerging Projects

Project Name

Description

DPH – ZSFG Remaining Brick Buildings Seismic Upgrade

The Department of Public Health continues to own seismically-deficient buildings, with no identified funding to retrofit. These include Buildings 1, 10, 20, 30, 40 and 100.

DPH – DPH Clinics Patient Renewal and Upgrade Program

There are long outstanding needs at neighborhood clinics not covered by the 2016 Public Health and Safety G.O. bond, including exam room reconfiguration, renewal of interiors, renovation of nursing stations, and exterior work.

DPH – DPH Clinics Security Improvements

Security improvements are required at several neighborhood clinics, including security cameras, IT improvements, and monitoring capabilities. The total project scope and cost have not yet been defined.

HSA – 170 Otis Street Seismic Upgrade

Built in 1978, 170 Otis St. houses HSA executive offices and program administration. Addressing the building’s seismic deficiencies, which is possible for the basement and the ground floor only, is estimated to cost $3.3 million, but no funding source has been identified.

HSA – 170 Otis Street Tenant Improvements

HSA needs to remodel certain floors of 170 Otis Street in order to accommodate increases in staff and changes in job functions. The remodel would include new cubicles to increase capacity, demolition of existing walls, construction of new walls as needed, and any related subsystem renewals. The goal is to reduce energy and water use, increase capacity, and improve functionality of the space.

HSA – Office Space Reconfiguration Planning

HSA is currently undertaking a study to look at its existing and future uses and staffing levels for the purposes of maximizing efficiency of space use, streamlining and consolidating operations, preparing for projected increase in clients, and coordinating its facility layout with its changing business practices.

 

HOPE SF Map

Health + Human Services: Emerging Projects

Emerging Projects

Project Name

Description

DPH – ZSFG Remaining Brick Buildings Seismic Upgrade

The Department of Public Health continues to own seismically-deficient buildings, with no identified funding to retrofit. These include Buildings 1, 10, 20, 30, 40 and 100.

DPH – DPH Clinics Patient Renewal and Upgrade Program

There are long outstanding needs at neighborhood clinics not covered by the 2016 Public Health and Safety G.O. bond, including exam room reconfiguration, renewal of interiors, renovation of nursing stations, and exterior work.

DPH – DPH Clinics Security Improvements

Security improvements are required at several neighborhood clinics, including security cameras, IT improvements, and monitoring capabilities. The total project scope and cost have not yet been defined.

HSA – 170 Otis Street Seismic Upgrade

Built in 1978, 170 Otis St. houses HSA executive offices and program administration. Addressing the building’s seismic deficiencies, which is possible for the basement and the ground floor only, is estimated to cost $3.3 million, but no funding source has been identified.

HSA – 170 Otis Street Tenant Improvements

HSA needs to remodel certain floors of 170 Otis Street in order to accommodate increases in staff and changes in job functions. The remodel would include new cubicles to increase capacity, demolition of existing walls, construction of new walls as needed, and any related subsystem renewals. The goal is to reduce energy and water use, increase capacity, and improve functionality of the space.

HSA – Office Space Reconfiguration Planning

HSA is currently undertaking a study to look at its existing and future uses and staffing levels for the purposes of maximizing efficiency of space use, streamlining and consolidating operations, preparing for projected increase in clients, and coordinating its facility layout with its changing business practices.

 

HOPE SF Map

2022 - Health + Human Services: Deferred Projects

09. Health and Human Services

Deferred Projects

Project Name Description
DPH – ZSFG Building 80/90
Renovation & Seismic Retrofit
Constructed in 1934, Building 80/90 is a seismically deficient red brick building at the ZSFG campus that houses the urgent care clinic and several other clinics. These clinics will move to Building 5 to make room for a major seismic renovation of this structure.
The total project cost is estimated to be $200 million.
DPH – ZSFG Building 5 IT IDF Migration This project will migrate IT systems from old non-compliant closets into new Intermediate Distribution Frame (IDF) closets in Building 5. These systems include emergency and normal power needs and building mechanical infrastructure to provide cooling and ventilation. This infrastructure will support all technology and equipment that has a network/data component, security systems and patient/staff safety, telephone systems, and medical and lab equipment. 
The migration will be a multi-year effort, and is expected to cost $1 million per year.
DPH – ZSFG New Electrical Feed There is currently an ongoing project to replace chillers and cooling towers serving ambulatory care buildings on the ZSFG campus. While that project includes power distribution from the main electrical switchgear to the new electrical chillers, it requires power in excess of what is currently available from the PG&E substation. The hospital will need a new substation feed to the campus in order to provide enough power.
The estimated project cost is $2.75 million.
DPH – LHH Emergency Power This project will add emergency power to LHH, which was built to minimum code requirements. The current emergency electrical power is not sufficient for the needs of the hospital, a facility with an elderly, non-ambulatory, and immune-compromised patient population.
The estimated project cost is $5 million.
DPH – LHH Cooling Center During Fall of 2017 a heat wave maxed out the hospital’s air conditioning system, creating a health hazard for patients with compromised health. This project would provide air conditioning to a large gathering space that would allow moving all patients to a cool space where they could be monitored.
The estimated project cost is $1 million.
DPH – LHH C-Wing Renovation Renovation of the third floor of the C-wing would allow for the consolidation of an on-site ambient training environment that provides mandatory trainings and workforce development trainings. Construction documents for this project have been completed.
The estimated project cost is $1.5 million.