Public Safety

San Francisco Fire Department

  • Completed HVAC system comprehensive upgrades and replacements for Station 9, 14, 26, and Community Paramedicine at 1415 Evans.

  • Completed hose tower removal work at Fire Stations 6, 11, 12, 21 and 38. Hose-tower removal and replacement is in process for Fire Station 15.

  • Progressed Emergency Firefighting Water System (EFWS) improvements including
    the completion of Pump Station 2 seismic retrofit project, installation of new pipes on parts of 19th Avenue as well as at new developments in Mission Bay, and the Clarendon supply pipeline.

San Francisco Police Department

  • Completed server room upgrades in alignment with federal National Incident Based Reporting System standards at the Academy, Central Station, and Marine Unit.

  • Awarded contract to Construction Manager/ General Contractor to complete seismic retrofit and historic renovation of Ingleside Station.

  • Design finalized and contractors selected for Surge and PCD phase 1 construction at 1828 Egbert Ave. 

  • Completed replacement of men’s showers at Mission Station.

Other Public Safety Accomplishments 

  • Completed a renovation of the 911 Call Center in Spring 2024. The renovation project not only meets today’s needs but anticipates the growth and challenges associated with a 24/7 operation that is essential in the response to major emergencies.

  • Completed the Sheriff's Department Facilities Master Plan and Infrastructure Improvement Plan, documenting current
    and future capital needs across its jails and other facilities.

  • Completed plumbing upgrades for County Jail #6, including additional hot water heaters, new toilet privacy partitions, and sewer system repairs. 

 

911 Call Center Renovation
911 Call Center Renovation

Police Academy
Police Academy

 

 

Fire Department Division of Training Rendering
Fire Department Division of Training Rendering

back to top