The Plan proposes funding the majority of the City’s ongoing annual needs with General Fund dollars through the Pay-As-You-Go (Pay-Go) Program. These are typically smaller investments to maintain facilities and infrastructure in a state of good repair or fund critical infrastructure needs. Within the Pay-Go Program, projects are categorized as Routine Maintenance, ADA Facilities, ADA Public Right-of-Way, Street Resurfacing, Critical Enhancements, Facility Renewal, and Right-of-Way Infrastructure Renewal.
Table 1.3 provides a summary of the Plan’s planned funding for the Pay-Go Program by expenditure category. The planned investment over 10 years is $2.7 billion.
Pay-Go Program Funding (Dollars in Millions) |
FY26-30 |
FY31-35 |
Plan Total |
---|---|---|---|
Routine Maintenance |
109 |
140 |
249 |
ADA: Facilities |
9 |
9 |
18 |
ADA: Public Right-of-Way |
55 |
71 |
125 |
Street Resurfacing |
207 |
290 |
497 |
Enhancements |
50 |
50 |
100 |
Recreation and Parks Base Commitment |
71 |
71 |
142 |
Capital Contribution to Street Tree Set-Aside |
37 |
48 |
85 |
ROW Infrastructure Renewal |
52 |
107 |
158 |
Facility Renewal |
439 |
885 |
1,325 |
Total Projected Funding |
1,030 |
1,670 |
2,700 |