General Fund Departments
General Fund departments primarily rely on the General Fund to support their infrastructure needs. Table 1.2 outlines a program summary of planned General Fund department investments, as well as projects deferred from the Plan due to funding limitations.
General Fund Department Program Summary (Dollars in Millions) |
||
---|---|---|
Renewal Investments | FUNDED | DEFERRED |
Today's Backlogs | ||
Facilities | 610 | |
Streets | 189 | |
Subtotal | 799 | |
Projected for Next 10 Years | ||
Facilities | 605 | 125 |
Streets | 816 | 511 |
Other right-of-way assets | 421 | 109 |
Subtotal | 1,841 | 745 |
SUBTOTAL, RENEWALS | 1,841 | 1,544 |
Capital Enhancement Investments | FUNDED | DEFERRED |
Earthquake and Safety Improvements | ||
HOJ Relocation Projects | 546 | |
SFFD Neighborhood Stations and Critical Facilities Improvements | 286 | |
Emergency Firefighting Water System | 204 | |
District Police Stations | 196 | |
ZSFG Building 80/90 Renovation & Seismic Retrofit | 115 | |
ZSFG Bldg 5 Renovation & Seismic Retrofit | 110 | |
DPH Civic Center Buildings Relocation | 93 | |
JUV Relocation from Administrative Building | 65 | |
SFFD Ambulance Deployment Center Relocation | 40 | |
SFFD Bureau of Equipment Relocation | 98 | |
Other Earthquake & Safety Improvements | 320 | 11 |
Subtotal | 1,975 | 109 |
Disability Access Improvements | ||
Facilities | 12 | |
Sidewalk Improvements and Repair Program | 37 | |
Curb Ramps (ADA Right-of-Way Transition Plan) | 86 | |
Subtotal | 135 | |
Parks, Open Space & Greening Improvements | ||
Neighborhood Parks and Open Space G.O. Bond Projects | 300 | |
Other Parks, Open Space & Greening Improvements | 236 | 31 |
Subtotal | 536 | 31 |
Street Infrastructure Improvements | ||
Better Market Street | 134 | 359 |
Islais Creek and 4th Street Bridge Rehabilitation | 67 | |
Utility Undergrounding | 1,407 | |
Other Street Infrastructure Improvements | 797 | |
Subtotal | 201 | 2,563 |
Other Improvements | ||
SHF – County Jails #1 and #2 (425 7th Street) Strengthening | 82 | 225 |
Improvements at Chinatown and Mission branch libraries | 27 | |
DEM Facility Addition for 1011 Turk | 30 | |
Other Projects | 425 | 137 |
Subtotal | 564 | 362 |
SUBTOTAL, ENHANCEMENTS | 3,410 | 3,065 |
PLAN TOTAL | 5,251 | 4,609 |